Customer Profile: Ward & Burke Construction Ltd
Ward & Burke Construction Ltd. – Galway
- Established: 2001
- Sector: Civil engineering, specialising in critical infrastructure projects such as roads, bridges, and energy management.
- Revenue (2022): Over €400 million, reflecting sustainable growth and a solid market position.
- Presence: Operations across Ireland, the UK, the USA, and Canada, showcasing a robust international footprint.
- Focus: Commitment to sustainable development practices and proactive growth strategies.
Project Overview
- Location: Co. Cork, adjacent to the Douglas Golf Course, a popular recreational area.
- Objective: Enhance community safety by addressing significant concerns related to stray golf balls, which posed threats to passing vehicles and nearby residential areas.
Challenges Faced
- Height Limitations:
- The project required the installation of a 20-metre-high ball stop netting structure, significantly exceeding the conventional height of 11 to 13 metres. This posed substantial design and engineering challenges.
- Environmental Factors:
- Cork County is known for its unpredictable weather, including high winds and heavy rainfall. A thorough assessment of the netting’s structural integrity was essential to ensure safety under extreme conditions.
- Compliance and Safety:
- The design and installation needed to align with stringent local safety regulations. Ward & Burke aimed to reassure local residents and government representatives of the infrastructure’s safety standards.
Solutions Implemented by SNG
Identified Structural Solution:
SNG Sports Nets collaborated with a manufacturer experienced in high structures to develop an innovative tripod lattice tower design.
This design provided essential stability at the required height, ensuring the structure’s safety and durability.
Detailed Design and Development:
SNG’s engineering team created comprehensive 3D models of the proposed netting system and conducted simulations to evaluate its performance under various environmental conditions.
This rigorous analysis helped identify potential points of failure and allowed for necessary adjustments to enhance safety.
The team specified a 28mm mesh net, designed to effectively contain golf balls. For added durability, the net was coated with PVC, offering resistance against fraying and ensuring performance during challenging weather conditions.
Sample Production and Testing:
A prototype net was developed, allowing Ward & Burke to visualise the final product and conduct preliminary stress tests to ensure compliance with industry standards and local regulations.
Installation Planning:
To ensure a seamless installation process, SNG took several critical steps:
Materials Sourcing: High-quality fixings, cables, and safety equipment were sourced from reputable suppliers, guaranteeing the structure’s longevity.
Crane Rental: SNG arranged for a crane rental capable of reaching the necessary height, facilitating safe and efficient installation while minimising disruption to the surroundings.
Execution
SNG’s project management philosophy emphasises precision and responsiveness.
The SNG team effectively oversaw every project phase, from initial design to manufacturing and installation, ensuring timely delivery within the planned timeframe and budget.
Results Achieved
- Successful Installation: Despite the unpredictable weather typical of Cork, the netting structure was successfully installed. Strategic planning and innovative solutions contributed to a seamless installation process, showcasing the efficacy of SNG’s approach.
- Positive Community Impact: The completion of the ball stop netting installation has significantly improved safety for road users and local residents. Community feedback indicates a marked reduction in safety concerns and heightened confidence in their environment.
- Long-Term Economic Benefits: The project not only provides immediate safety improvements but also enhances Ward & Burke’s reputation as a proactive leader in infrastructure development, potentially leading to increased bidding opportunities for future public projects
Delivering a project of this scale has been rewarding. It highlights our capacity to innovate under pressure and exceed client expectations. We take pride in partnering with Ward & Burke on this pioneering project
Barry, SNG Sports Nets
Conclusion
This case study showcases the successful partnership between SNG Sports Nets and Ward & Burke Construction in overcoming substantial challenges to deliver an innovative ball stop netting solution. The project sets a new benchmark for netting heights in Ireland while reaffirming both companies’ commitments to safety, innovation, and client satisfaction.
Lessons Learned
- Adaptability is Key: Flexibility in engineering design is essential, especially when faced with unique challenges like unprecedented height requirements and adverse weather.
- Collaboration Drives Innovation: Strong partnerships with specialised manufacturers can result in innovative solutions that surpass traditional methods.
- Community Engagement: Addressing local safety concerns fosters community trust and enhances relationships, leading to better project outcomes.
- Proactive Risk Management: Thorough risk assessments regarding environmental factors and regulatory compliance are crucial for a smoother project lifecycle.
- Commitment to Excellence: Continuous dedication to safety, quality, and innovation is fundamental to meeting client needs and establishing a lasting reputation
By reflecting on these insights, SNG Sports Nets and Ward & Burke can continue to refine their processes and maintain their commitments to excellence in future projects.
The collaborative spirit and innovative thinking demonstrated in this endeavour will undoubtedly inform their future efforts in tackling complex engineering challenges.